Accent were hired to replace the existing chillers with 2 Daikin Chillers.

Case Study - Business Park

Project Details

Sector: Commercial

Project: Business Park

Client: Calibre Building Services Ltd

Project Overview: Chiller

Duration: 2 x 3 weeks

Value: £190,000

Scope Of Works
Accent were employed to carry out the replacement of 2 Carrier Chillers which were beyond economical repair. The replacement Chillers were 2 Daikin Air Cooled  High Efficiency Screw Chillers. The installation included Acoustic attenuation and was carried out over 2 weekends to ensure cooling was available to the building at all times.